Power Generation – Plant design

About The Project

BASE was hired to create an FEL and FEED study for a new 22MW power plant in Alberta. The objective was to analyze different scenarios to build a power plant utilizing various engines and fuels.  The new facility required Low Emissions, black start capability, high reliability, and be remotely operatable with low-cost operation. BASE’s knowledge of cost-effective, safe, and reliable power service for power plants was a key component of the project.  The FEL and FEED studies are complete and Base will begin the design/implementation phase upon receiving funding approval.

Improvements/Results

  • Researched and negotiated with multiple vendors to determine unit selection that met client criteria
  • Provided solutions that met the key requirements of high reliability, low cost and remote operations
  • Unit emissions are lower than other similar units
  • Preliminary standards and layouts were created
  • Regulatory approvals are complete
  • Vendor pricing agreements have been negotiated
  • Provided TIC to financers for high certainty of project funding

 

Phase
FEL 1
Business Planning
Goal(s)
  • Business Opportunity
  • Classify Risks
  • Align Objectives
  • Business Planning
Cost Estimate
Order of Magnitude
+/-50%
Deliverables
  • Business Case
  • Requirements
  • Objectives
  • Regulatory Plan
  • Decision Reviews
  • Refine Costs Estimates
  • Project Exec Plan (PEP)
  • Project Risk Assesment
  • Draft Pipeline Corridor
Phase
FEL 2
Conceptual Design
Goal(s)
  • Confirm Visibility
  • Select Optimum Solutions
  • Facility Planning
  • Economics
Cost Estimate
Preliminary
+/-30%
Deliverables
  • Pipeline Route
  • Process Descriptions
  • Pipeline System Params
  • SCADA/Telecom Req.
  • Infrastructure Layouts
  • Equip List/MTO
  • Regulatory Plan
  • HSE Plans
  • Refine Estimate
  • Schedule
  • Prelim Drawings
Phase
FEL 3
Basic Engineering
Goal(s)
  • Project Planning
  • Define for Execution (activities & deliverables)
  • Scope
  • Execution Plan
Cost Estimate
Budget
+/-20% to 15%
Deliverables
  • Final Route
  • Design Basis
  • Drawings
  • Detailed Cost & Schedule
  • Procurement Strategies
  • Info for Det. Engineering
  • Risk Assesment
  • Safety Assesment
  • Operations Assesment
Phase
Engineering & Construction
Goal(s)
  • Engineering
  • Procurement Equipment
  • Construction Management
  • Testing
Cost Estimate
Control
+/- 15% to 10%
Deliverables
  • Detailed Drawings
  • Construction Specs
  • Final Routing
  • Permitting
  • Land Acquisition
  • Surveys
  • Center Line Staking
  • Re-routes
  • As-built Data
  • Regulatory/Permits
  • HSE
  • Handover
Phase
Operations
Goal(s)
  • Commission
  • Turnover
  • Startup
  • Operate
Cost Estimate
Definitive
+/- 10% to 5%
Deliverables
  • Data Books
  • Commissioning Planning
  • Start-up Plan
  • Pre-commissioning
  • Commissioning
  • Performance Testing
  • GIS/PODS Database